How to Choose an Interior Design Company: A Complete Guide to Quotations, Project Duration, Warranty and Site Supervision
- First, distinguish the roles: An interior design company handles design, drawings and project management, while a renovation contractor carries out the construction. One company can do both, but the quotation must list the design fee and the construction fee separately — never as a single lump sum.
- Quotations must be "comparable": Every item needs a quantity, unit price and sub-total. In 2024, the Consumer Council commissioned the Hong Kong Institute of Surveyors to assess 40 preliminary quotations; the average score was only 58 out of 100, and just 8% scored above 80.
- Deposit should not exceed 40%: The Consumer Council recommends payment in 4 instalments by stage or by project phase, with the first deposit not exceeding 40% of the total contract sum.
- Wall demolition, plumbing alterations and electrical alterations all carry statutory requirements: Before signing, check the contractor's registration on the registers of the Buildings Department, the Electrical and Mechanical Services Department and the Water Supplies Department, and collect the statutory documents on completion (e.g. the electrical completion certificate WR1).
- The contract must cover delay and defect rectification: Completion date, how delay is handled, the defect list and the scope of the warranty period — missing any one of these four is a recipe for future disputes.
- Design company vs renovation contractor: who is responsible for what
- Before signing: write your own requirements list first
- The 12 areas to check in a quotation
- The four most common quotation traps
- Drawings, 3D renders and "free design"
- Project duration: how to write it into the contract to give it teeth
- Payment schedule: four instalments, deposit cap, final payment
- Site supervision: five inspection points
- Which works are regulated by law
- Warranty period and defect list
- Checklist of essential contract clauses
- What to do if things go wrong: complaints, mediation, Small Claims Tribunal
- Frequently asked questions
- References
1. Design company vs renovation contractor: who is responsible for what
When Hong Kong people talk about "renovation", they usually conflate two things: design and construction. But the contractual responsibilities of the two are entirely different, as are their fee structures. The most common result of confusing them is that "design revisions until you're satisfied" drags on indefinitely, or that "construction with design included" turns into slapdash drawings.
| Role | Main work | Fee basis (common wording) | What you need to watch closely |
|---|---|---|---|
| Interior design company | Site measurement, space planning, material selection, construction drawings, 3D renders, liaising on the project on the client's behalf | Per square foot of saleable area, a percentage of the total contract sum, or a fixed design fee | How many rounds of revisions the design fee covers, the depth of the drawings (floor plans / elevation drawings / construction detail drawings), and whether on-site supervision is included |
| Renovation contractor | Demolition, wet trades, plumbing and electrical, carpentry, painting, installation | Itemised quotation per work process, or "labour and materials included" | The quantity, unit price, material brand and model, and construction method for each work process |
| Engineering consultant / project management | Tender review, drawing review, monitoring progress and quality, and acceptance inspection on the owner's behalf | Fixed fee or monthly fee | Independence: the consultant should not also be a bidding contractor |
The Consumer Council's 2024 study on home renovation pointed out that Hong Kong currently has no specific legislation or regulation governing the operation of home renovation companies and their services; in the event of a dispute, consumers can only rely on general consumer protection legislation and common law. In other words, the contract and quotation you sign are your only safety net.
The same study also noted that between 2017 and 2023 the Consumer Council received a total of 1,205 complaints about home renovation services, involving a total sum of over HK$270 million, averaging close to HK$230,000 per case. The figures make one thing clear: these are not disputes over a few thousand dollars, but decisions that can affect a family's cash flow for years.
2. Before signing: write your own requirements list first
Most people turn up to meet a designer with nothing but a pile of Pinterest images. The designer has no choice but to guess; guess wrong and the drawings have to be revised, and revisions mean extra cost or delay. The safer approach is to write your own "requirements brief" first, covering at least the following six items:
- How many people will live there, and will the household grow in the next five years: This determines the number of rooms and the amount of storage — more important than style.
- What must be kept and what must be changed: For example, you want to keep the existing flooring, or the kitchen must be converted to open-plan (note: open kitchens are subject to fire safety requirements — see section 9).
- Storage inventory: Communicate in "number of items" rather than "is there enough space" — for example, 200 books, 3 suitcases, 1 bicycle.
- Budget ceiling and the "must not exceed" bottom line: Write down a total figure and state clearly how much overrun would make you reconsider.
- Time constraints: When you need to move in and when your tenancy expires directly affect how long a project duration you can accept.
- Special needs: Grab rails for the elderly, impact protection for children, pets, wheelchair access, soundproofing for a workspace, etc.
The Consumer Council's 2024 consumer survey showed that the main source of renovation information for respondents was family, relatives and friends (93%), followed by online channels (50%); when choosing a company, the two major considerations were price and discounts (79%) and company reputation (73%). Recommendations from friends are worth considering, but remember: your friend's flat conditions and requirements differ from yours, and a good reputation does not mean the company is right for you.
3. The 12 areas your quotation must get right
In 2020, the Consumer Council posed as a consumer for the first time and asked 11 renovation and interior design firms to quote for a full flat renovation of a unit of about 400 sq ft with two bedrooms, a living room, a kitchen and a bathroom, and engaged the Hong Kong Institute of Building Inspection to score the quotes against 10 criteria. The 11 firms averaged only 5.5 points out of 10; only 2 scored 9, while the two worst scored just 1 and 2 respectively. The weakest area was "contract terms": only 2 firms set them out in detail, 6 mentioned them only briefly, and 3 made no mention at all.
Of the same group of firms, only 5 stated an estimated construction period in their quotation. Below are the 12 areas identified by the Consumer Council, which you can use directly as a checklist:
| Area | What the quotation must show |
|---|---|
| 1. Demolition | A demolition and retention list; the location of structural walls; temporary protection for the building's common areas; who is responsible for construction waste disposal and the Government levy |
| 2. Plumbing | Where the replacement scope starts (the first gate valve inside the flat / the floor-level water meter); exposed or concealed pipes; the material, place of origin and brand of pipes and fittings |
| 3. Electrical | How each socket point is charged (per point / per circuit); the model or series of faceplates; whether the consumer unit is newly installed |
| 4. Tiling and screeding | The actual area to be worked on; who supplies the base and finish materials respectively; the location of waterproofing, the waterproofing material, the height of the waterproofing layer, and whether a water test is included |
| 5. Painting | The number of coats of primer and topcoat respectively; whether "full scraping" (剷底) is included; whether special-function paints (e.g. anti-formaldehyde) are charged separately |
| 6. Carpentry and furniture | The unit of measurement for each piece of furniture (linear feet / feet of width), the main materials, and who supplies the hardware; once confirmed, drawings, dimensions and colour samples must be signed off |
| 7. Cleaning | Whole-flat or partial cleaning; whether pest control and formaldehyde removal are included (in the Consumer Council's test, not one firm mentioned them) |
| 8. Other installations | Who supplies and installs the toilet, shower cubicle, sanitary ware, light fittings and electrical appliances; how aluminium windows and scaffolding are charged |
| 9. Payment method | The amount of each stage, the trigger conditions (by item or by construction period), and when the final balance is payable |
| 10. Contract terms | The commencement and completion dates and their definitions; circumstances affecting the construction period; the procedure for additional works; the warranty period; default and termination arrangements |
| 11. Construction period | Working days or calendar days; whether the production period for custom-made furniture is included |
| 12. Insurance | Who takes out the third-party liability insurance / renovation works insurance, the sum insured, and the scope of cover |
A 2024 study quantified how common "not detailed enough" is: of 40 preliminary quotations, 100% stated the total contract sum and 93% set out the payment details, but only 38% listed all work items, 28% stated the quantity of each work item, and 20% stated unit prices; as for a "statement of legal and regulatory compliance", only 20% included one, and a "statement of compliance with property management company requirements" appeared in just 8%.
4. The four most common quotation traps
Trap 1: Total "to be determined", unit prices "to be negotiated"
"Number of socket points to be determined, adjusted up or down once confirmed" is standard industry wording and is not necessarily a problem in itself; the problem is that no unit price is stated. At the same time, if you add two sockets on site at short notice, you can be charged a price you never budgeted for. Requiring the other party to state in the quotation how each socket point is charged is the only effective safeguard. In the Consumer Council's 2020 test, 5 firms did not state how each socket was charged, and only 2 clearly specified the faceplate model.
Trap 2: "Labour and materials included" can be defined very broadly, or very narrowly
Painting is described as "labour and materials included", but the number of primer and topcoat layers is not stated; tiling is described as "labour and materials included", but the finish materials (tiles, mosaics, stone) are for you to buy yourself. In the Consumer Council's test, 8 firms said "labour and materials included", of which 7 did not specify the number of coats of primer or topcoat. Before signing, ask of each item: "Which material, and how many layers, are included?"
Trap 3: Waterproofing left unclear
Waterproofing is the most easily overlooked item in tiling works, yet the most expensive when things go wrong (it affects the unit below and can escalate into a water seepage complaint). In that test, 7 firms stated the location of waterproofing works, but fewer than half set out the waterproofing material details, the height of the waterproofing layer, or whether a leakage test would be provided.
Trap 4: Work starts before the quote
Hong Kong Customs has handled real cases: one renovation contractor claimed certain works were included free of charge, then charged extra for the same items, and made false statements about the price and supplier of electrical appliances, with the works contract amounting to $370,000; another made a misleading omission about the total project price, collecting $100,000 first and then demanding a further $80,000 for the same works after commencement. Both firms were ultimately sentenced to 80 and 180 hours of community service respectively for contravening the Trade Descriptions Ordinance, and one was also ordered to compensate the victim $25,000.
5. Drawings, 3D images and "free design"
"Free design" usually comes with two conditions: first, you must use that company's construction services; second, the depth of design is limited (mostly just a floor plan plus a few renderings, with no construction detail drawings). If you plan to find your own contractor to carry out the works, you should budget to pay a separate design fee for a full set of drawings.
Either way, you should confirm the drawing list before signing, because the drawings are the standard for acceptance:
- Floor plan: partitions, doors and windows, furniture positions, dimensions
- Elevations: the finished surface of each wall, light positions, socket heights
- Construction / detail drawings: how false ceilings, light troughs, raised floors and waterproofing terminations are built
- Furniture drawings: the elevation, internal layout and hardware positions of each custom-made piece
- Material schedule: brand, model, colour code, finish, preferably with samples attached
The Consumer Council recommends that, after the quotation for custom-made furniture is confirmed, the contractor should provide drawings, detailed dimensions, material samples and colours for the consumer to select and sign off, to serve as the basis for later reference. A signed furniture drawing is worth more than any verbal assurance.
6. Construction period: how to write it into the contract so it has teeth
A vaguely worded "construction period" is as good as none. Below are some common wording problems and how they should be rewritten:
| Vague wording | Should be rewritten as |
|---|---|
| "The works will take about 60 days" | "Commencing on 5 January 2027 and completed on or before 20 March 2027, totalling 60 working days" — state both calendar days and working days, and define what is excluded (e.g. black rainstorms, Typhoon Signal No. 8, suspension of works by the management office) |
| "Excluding the custom-made furniture period" | List separately: on-site works X working days; furniture production and delivery/installation Y working days; combined completion date Z |
| "In the event of delay, the parties shall discuss separately" | State the calculation of liquidated damages for delay (e.g. a certain percentage of the total contract sum per day of delay) and the cap |
In the Consumer Council's 2020 test, only 5 firms stated an estimated construction period in their quotation; one wrote "60 working days" but excluded the period for custom-made joinery. The Consumer Council reminds consumers that the quotation should state the construction time for both.
If you have to move out, a delay in the construction period translates directly into rental expense. Writing this potential cost into the contract as a term is a reasonable approach.
7. Payment schedule: four stages, deposit cap, final balance
The Consumer Council explicitly recommends that the first-stage deposit should not exceed 40% of the total contract sum, because if the works are abandoned early on, the consumer will suffer a significant financial loss. It cites the Hong Kong Institute of Building Inspection's recommendation that payment should preferably be made in 4 stages, with the trigger conditions for each stage (by completion of items or by construction period) stated in the quotation.
| Stage | Example 1 | Example 2 |
|---|---|---|
| Stage 1 | 10% initial deposit + 30% main deposit | 10% initial deposit + 20% main deposit |
| Stage 2 | 30% | 30% |
| Stage 3 | 20% | 30% |
| Final stage | 10% | 10% |
Wording to avoid: "Stage 2: 40%", "50% at mid-project" — who defines "mid-project"? In the Consumer Council's test, 4 firms set payment dates using such hard-to-quantify criteria. The final balance should be paid only after acceptance is completed and the defect list is signed.
8. Site supervision: five checkpoints
A 2024 Consumer Council survey found that the three biggest worries for consumers during construction were: projects being left unfinished ("rotten tail") (73%), poor workmanship (61%), and renovation companies going missing after receiving payment (59%). Rather than chasing remedies afterwards, it is better to keep records during the process. At each of the following five checkpoints, you should take photos and note the date every time you visit the site:
- Before work starts: Verify the contractor's registration (see Section 9), confirm the renovation application and deposit arrangements with the building's management office, and photograph existing common areas and lifts for the record.
- After demolition, before screeding: Confirm that structural walls have not been wrongly demolished, that the positions of water supply and drainage pipes match the drawings, and that electrical back box positions have been fixed. This is the only window when changes can be made at low cost.
- After waterproofing, before tiling: Require a leakage test (commonly known as a water test), ponding water in the bathroom and kitchen for at least 24 hours, and photograph the water level for the record. If this step is skipped, it will be extremely difficult to establish liability for leaks later.
- When carpentry begins: Check that the brands of boards and hardware match the quotation, and measure whether the internal clear depth of cabinets is sufficient (many disputes stem from "it looked deep on the drawing but turned out shallow").
- Final inspection on completion: Go through each item against the drawings, switch on every electrical switch, every tap and every door, compile a defects list and require completion dates to be stated in writing.
The Consumer Council survey also showed that 80% of respondents said they would not hire a third party to inspect work quality, mainly because of the high cost. If you do not engage a professional inspector, you should at the very least "photograph before each stage is completed, and confirm every verbal promise in writing via WhatsApp".
9. Which works are regulated by law
This is the most important section of the whole article. In its 2024 study, the Consumer Council enquired about wall demolition works as a mystery shopper and found that three-quarters of home renovation companies said they could proceed with wall demolition simply by reviewing the unit's floor plan, without further verifying the nature of the wall; likewise, three-quarters said the kitchen door could be changed to a sliding door, which may contravene the fire safety provisions of the Buildings Ordinance. In other words: a contractor saying "it's fine" does not mean it is legal.
| Works | Statutory requirements | How you can verify |
|---|---|---|
| Demolition or alteration of structural walls, beams, columns | An authorized person and registered structural engineer must be appointed to assess feasibility, plans must be submitted to the Buildings Department, and the works must be carried out by a registered contractor after approval and consent are obtained | The Buildings Department's "Search for Registered Professionals or Contractors" register; request the approval documents |
| Erection or alteration of non-load-bearing brick walls, thickening of floor slabs | These are minor works under the Building (Minor Works) Regulation; prescribed building professionals and/or prescribed registered contractors must be appointed according to the class, and the Buildings Department must be notified before and/or after completion | Check whether the contractor holds registration of the corresponding class and type |
| Alteration of bathrooms/kitchens (involving drainage pipes) | Alteration of drainage pipes must be notified to the Buildings Department under the minor works control system, and a prescribed registered contractor must be appointed; a proper waterproofing layer must also be provided to avoid water seepage nuisance to the floor below | As above; also require waterproofing water test records |
| Replacement of windows | Depending on the size, height and distance from the floor, this may be minor works (requiring a prescribed building professional/registered contractor), or plans may need to be submitted and approved before the works can proceed | Ask the Buildings Department or an authorized person first; do not rely on the contractor's verbal judgment |
| Fixed electrical installations (adding sockets, altering distribution boards, connecting air-conditioners) | Electrical work must be carried out by a registered electrical contractor, and a completion certificate (Form WR1) must be issued after completion | The Electrical and Mechanical Services Department's "Registered Electrical Contractors" register; obtain the original WR1 |
| Internal plumbing systems (altering pipes, adding taps) | Construction, installation, alteration or removal of internal plumbing systems requires written permission from the Water Authority; specified plumbing works must be carried out by designated persons such as licensed plumbers | The Water Supplies Department's register of licensed plumbers; check the permission documents |
| Converting a kitchen into an open kitchen | May involve fire safety requirements; it is not merely a design choice | Consult an authorized person first; do not accept suggestions to "help you avoid inspection" |
Conversely, general interior painting, plastering, tiling, and repair or replacement of sanitary fittings are exempted works under section 41(3) of the Buildings Ordinance, requiring neither prior approval from the Buildings Department nor the appointment of building professionals or registered contractors — but they must still comply with standards on fire safety, structural safety and drainage works.
The minor works control system currently regulates 187 minor works items in three classes: Class I 58 items (high risk), Class II 68 items (medium risk) and Class III 61 items (low risk). For Class I and II works, documents must be submitted not less than 7 days before the works commence; for Class III works, no prior submission is required, but documents must be submitted within 14 days after completion.
10. Warranty period and defects list
Hong Kong has no specific legislation stipulating the length of the warranty period for home renovation; the scope of the warranty depends entirely on what is written in the contract. So the four words "one-year warranty" must be accompanied by three questions:
- What is covered: Does it cover workmanship only, or materials as well? Does it cover waterproofing leaks? Does it cover problems caused by human damage, alterations or natural wear and tear?
- Who does it: Will the original contractor do it themselves, or can it be subcontracted? Is there a charge for on-site inspections?
- When is it done: Within how many working days after notice will they attend? What happens if they are late?
As for defects, the Consumer Council recommends that at the end of the works both parties draw up a defects list stating each problem, the remedy and the completion date, linked to payment of the final balance. In the Consumer Council's 2024 survey, the three most common types of disputes were: project delays (61%), poor workmanship (39%), and renovation companies refusing to "fix defects" (30%).
In practice, on the day of final inspection you should: bring all drawings and the materials schedule; try every electrical switch, tap, door hinge and drawer; shine a torch at an angle on walls to check whether the plastering is level; pour water on bathroom and kitchen floors to test the drainage gradient; photograph all defects; and only then sign the defects list.
11. Checklist of essential contract terms
The Consumer Council's 2024 study recommended establishing a standard quotation template, structured into three major areas covering 20 main aspects. You can use the checklist below directly, asking the other party item by item "is this written down?". If three or more items are missing, you should require them to be added before signing.
- Company full name, business registration number, registered contractor number (if applicable), contact person and address
- Scope of works and detailed items: quantities, unit prices, subtotals, total contract sum
- Description of workmanship standards (e.g. number of paint coats, tile joint width, levelness requirements)
- Commencement date, completion date, and the definitions of both
- Circumstances that may affect the programme, and how delays will be handled and compensated
- Procedure for additional works: written quotation, signed confirmation, then work begins
- Payment schedule: amount of each instalment, trigger conditions, final balance arrangements
- Deposit amount (not exceeding 40% of the total)
- Basis of pricing for variations or additional works
- Declaration and arrangements for subcontracting (sub-contracting down the chain)
- Health and safety precautions
- Protection measures for completed works during construction
- Declaration of compliance with the law (including fire safety, structural, drainage and electrical)
- Declaration of compliance with the property management company's requirements
- Completion standards and post-completion cleaning arrangements
- Defects arrangements: list, completion deadline
- Warranty period: scope, duration, response time
- Terms, arrangements and compensation for termination of contract
- Insurance liability: which party purchases third-party liability insurance, and the insured amount
- Dispute resolution method (mediation/arbitration)
The Consumer Council also recommends that the standard template may include a cooling-off period of not less than 7 days, as well as escrow or trust arrangements for payments, to reduce the risk of funds being misappropriated. These are currently recommendations and not yet statutory requirements, but you can proactively ask for them to be written into the contract.
12. When things go wrong: complaints, mediation and the Small Claims Tribunal
In the Consumer Council's 2024 survey, about one in five (19%) of the respondents who had carried out renovation works said they had a dispute with the company they engaged. The recommended order of handling is as follows:
- Written negotiation: Put all your grievances into a list (dates, items, photos, demands) and send it to the other party by email or WhatsApp, requesting a written reply. Verbal negotiation will almost certainly turn into "you said it, I didn't".
- Complain to the Consumer Council: The Consumer Council can mediate, but it has no enforcement powers; if mediation fails, you still have to pursue recovery through other channels.
- Involving unfair trade practices: You may report to Hong Kong Customs. False trade descriptions, misleading omissions and the like are criminal offences under the Trade Descriptions Ordinance.
- Monetary claims: For claims not exceeding $75,000, you can file at the Small Claims Tribunal, where the procedure is simpler and the fees lower, and neither party may be represented by a lawyer in court. For amounts exceeding $75,000, you would have to consider the District Court, or give up the excess in order to stay at the Small Claims Tribunal.
- Mediation or arbitration: If the contract already contains a mediation clause, you may first deal with the matter through mediation; only if mediation fails should you consider arbitration or litigation.
13. Frequently Asked Questions
Is it a good idea to engage one company to handle both interior design and renovation?
It is possible, but the quotation must list the design fee and the works fee separately, and clearly state how many rounds of revisions the design fee covers, the depth of the drawings, and whether on-site supervision is included. If the company provides both design and construction, what you lose is an independent third party to review the drawings and carry out acceptance inspections for you; the remedy is to write the acceptance standards in extremely detailed terms (see sections 5 and 10).
Is the company with the cheapest quotation the best value?
The Consumer Council's 2024 study found that, for some companies, the preliminary estimates given before a detailed quotation differed from the final quotation by between −32% and +28%. So "preliminary estimates" cannot be compared directly; only formal quotations of the same specification and the same level of detail are meaningful. A low price may also mean omitted items (for example, not including water-tightness testing for waterproofing, or not including cleaning), which are then added item by item after signing.
Is it essential to verify the nature of a wall before demolishing it?
Yes. In the Consumer Council's mystery-shopper enquiries, three-quarters of the companies said a wall could be demolished simply by looking at the floor plan, which is unsafe. If structural walls, beams or columns are involved, an authorised person and a registered structural engineer must be appointed to assess the matter and submit plans to the Buildings Department; if it is a non-load-bearing wall, it may still constitute minor works, which must be carried out by a prescribed registered contractor with notification to the Buildings Department. The consequences of demolishing a structural wall without authorisation fall on the owner.
For converting a kitchen to open-plan, the designer says there is no problem — should I believe it?
Do not rely on a verbal judgment alone. The Consumer Council's study points out that three-quarters of the companies surveyed said the kitchen door could be changed to a sliding door, when doing so may contravene the fire safety requirements of the Buildings Ordinance. An authorised person should be consulted first; if any company suggests "helping you get around the fire inspection", that in itself is a serious red flag.
How many stages should payment be divided into? What deposit is reasonable?
The Consumer Council recommends four stages, and expressly states that the first-stage deposit should not exceed 40% of the total contract sum. The trigger conditions for each stage should be written in quantifiable terms, for example "pay the 2nd stage after the wet trades are completed and accepted", rather than "pay 50% at mid-stage of the works".
How long is a warranty period usually?
There is no statutory standard in Hong Kong; the length is specified in the contract. The key is not the number but the scope: whether waterproofing and seepage are covered, whether materials are covered, whether on-site inspections are chargeable, and how many days after notice the matter will be dealt with. Writing these four points into the contract is more practical than bargaining for a few extra months of warranty.
If the works are left unfinished, how much can I recover?
It depends on the contract, the amount already paid, the amount of works completed and the actual loss. If false statements or misleading omissions are involved, you may report to Customs; monetary claims not exceeding $75,000 can be filed at the Small Claims Tribunal. The reality is that even if you win, the other party may not have the ability to pay — so the payment schedule (cap on deposit, final payment tied to acceptance) is the most effective risk control.
How do I check whether a company is a registered contractor?
The Buildings Department website has a register for "Search for Registered Professionals or Contractors", where you can enter a name or registration number and select the grade, type and operating district of minor works contractors. For electrical works, check the Electrical and Mechanical Services Department's register of "Registered Electrical Contractors"; for plumbing works, check the Water Supplies Department's register of licensed plumbers. The name must match the company name on the quotation for it to check out.
14. References
- Consumer Council: "Consumer Council Proposes 4 Major Recommendations to Strengthen Regulation of the Home Renovation Industry" (2024-02-21)
https://consumer.org.hk/tc/press-release/p-home-renovation-study-report - Consumer Council: "Proposing Regulation of Home Renovation to Build Comfortable and Happy Homes" Study Report
https://consumer.org.hk/tc/advocacy/study-report/home_renovation_study - Consumer Council: "Home Renovation Industry – Better Governance for Creating Comfortable Homes" Full Report (PDF)
https://consumer.org.hk/f/initiative_detail/432464/459600/Home - Full Report_v2.pdf - Consumer Council: Study Report Chinese Presentation Deck (PDF)
https://consumer.org.hk/f/initiative_detail/432464/459683/H - Presentation Deck (Chinese)_v3.pdf - Consumer Council: "First Practical Test of Home Renovation Quotations Finds Most Are Vague and Unclear" (2020-11-16)
https://consumer.org.hk/tc/press-release/529-quotation-details-for-renovation - Consumer Council: "Renovation Quotations Must Be Detailed — A Step-by-Step Guide to the 12 Major Areas"
https://consumer.org.hk/tc/article/529-Renovation/529_renovation_items - Consumer Council: "Renovation Works Not Meeting Required Standards Lead to Disputes — Detailed Contracts and Regular Follow-up to Avoid Arguments"
https://consumer.org.hk/tc/press-release/530-renovation-complaint - Buildings Department: Alteration and Addition Works in Domestic Premises (FAQ)
https://www.bd.gov.hk/tc/resources/faq/index_alteration_and_addition_works_in_domestic_premises.html - Buildings Department: Introduction to the Minor Works Control System (three classes and submission deadlines)
https://www.bd.gov.hk/tc/building-works/minor-works/introduction-to-minor-works-control-system/index.html - Buildings Department: Minor Works Control System — Indoor Renovation/Alteration and Subdivision of Flats into Subdivided Units (booklet PDF)
https://www.bd.gov.hk/doc/tc/resources/pamphlets-and-videos/MWCS_interior_c.pdf - Buildings Department: Registered Minor Works Contractors (Companies)
https://www.bd.gov.hk/tc/resources/registration-guides/index_RMWC_company.html - Buildings Department: Search for Registered Professionals or Contractors
https://www.bd.gov.hk/tc/resources/online-tools/registers-search/registrationsearch.html - Buildings Department: Technical Guidelines on the Minor Works Control System (Chapter 5, Exempted Works)
https://www.bd.gov.hk/doc/tc/resources/codes-and-references/code-and-design-manuals/MW/TG_c/TGc_ch05.pdf - Buildings Department: Subdivided Units (SDUs) FAQ
https://www.bd.gov.hk/tc/resources/faq/index_subdivision_of_a_flat_subdivided_units.html - Electrical and Mechanical Services Department: Register of Registered Electrical Contractors
https://www.emsd.gov.hk/tc/electricity_safety/registers/registered_electrical_contractors/index.html - Electrical and Mechanical Services Department: Electrical Safety in Subdivided Units (electrical work must be carried out by registered electrical contractors; WR1 Completion Certificate)
https://www.emsd.gov.hk/tc/electricity_safety/electricity_information/sub_divided_unit_electrical_safety/index.html - Water Supplies Department: Employing a Licensed Plumber (Sections 14 and 15 of the Waterworks Ordinance)
https://www.wsd.gov.hk/tc/customer-services/other-customer-services/employ-a-licensed-plumber-/index.html - Water Supplies Department: Practice Guide on Carrying Out Plumbing Works (PDF)
https://wsd.gov.hk/filemanager/tc/content_1768/practice-guide-on-carrying-out-plumbing-works-c.pdf - Hong Kong e-Legislation: Buildings Ordinance (Cap. 123)
https://www.elegislation.gov.hk/hk/cap123 - Hong Kong e-Legislation: Electricity Ordinance (Cap. 406)
https://www.elegislation.gov.hk/hk/cap406 - Hong Kong e-Legislation: Waterworks Ordinance (Cap. 102)
https://www.elegislation.gov.hk/hk/cap102 - Hong Kong e-Legislation: Trade Descriptions Ordinance (Cap. 362)
https://www.elegislation.gov.hk/hk/cap362 - Hong Kong e-Legislation: Small Claims Tribunal Ordinance (Cap. 338)
https://www.elegislation.gov.hk/hk/cap338 - Hong Kong Customs: Press Release — Two Renovation Works Contractors Convicted of Contravening the Trade Descriptions Ordinance
https://customs.gov.hk/tc/customs-announcement/press-release/index_id_336.html - Hong Kong Customs: Presentation on the Fair Trading Provisions of the Trade Descriptions Ordinance (PDF)
https://eservices.customs.gov.hk/MSOS/downloadFile?id=355640 - Government Press Release: Claim Limit of the Small Claims Tribunal (Written Reply to the Legislative Council, 2026-10-21)
https://www.info.gov.hk/gia/general/202610/21/P2026102100360.htm
完整目錄加入連結